How to work out a progress claim: a worked example

A progress claim is the work done to date, less retention, less what you have already claimed, plus GST. This guide builds one line by line, with a fictional example that claims $29,450 plus $2,945 GST.

If a head contractor pays you by monthly progress claims, each claim has to answer one question. How much have you earned to date, and how much of it is still unclaimed? Variations, retention and last month's claim all change the answer.

This guide builds one claim, line by line, in any spreadsheet. It then sets out what a claim must contain in New South Wales, Victoria and Queensland, as each state's pages publish it. All amounts are in Australian dollars, and GST is shown separately.

What a progress claim is made of

Five figures go into every claim:

  • Contract sum: the price in your contract, before GST.
  • Approved variations: changes to the work that the client has approved, each with its own price. The contract sum plus these is the adjusted contract sum.
  • Work to date: the value of the work done since the start, line by line.
  • Retention: the part of that value the client holds back until the dates in your contract.
  • Previous claims: what you have already claimed, after retention.

The formulas, with every amount before GST:

Adjusted contract sum = contract sum + approved variations
Work to date          = sum of (line value × per cent complete), line by line
Retention to date     = the lower of (work to date × retention rate) and the retention cap
Net value to date     = work to date − retention to date
This claim            = net value to date − previous claims (after retention)
GST                   = 10% × this claim, if you're registered for GST
Claim including GST   = this claim + GST

Work to date counts everything since the start, not only this month. Subtracting previous claims is what leaves this month's amount.

Subtract what you have claimed, not what the client has paid. If an earlier claim is still unpaid, show it on its own line below this month's amount. The NSW and Queensland pages read for this guide both say a claim can carry earlier unpaid amounts. Check how your state treats them.

GST is 10% on most goods and services. If you're registered, you collect it from your customer (business.gov.au). How GST applies to the part held back as retention is a question for your registered tax or BAS agent. This guide adds 10% to the amount you ask to be paid now and doesn't settle that question.

Per cent complete: by line, not for the whole job

A whole-job per cent hides which lines are done. In the example below, 47.4% of the adjusted contract sum is complete by value. Two lines are done, two are part-way and one hasn't started. Estimating "about half" for the whole job would put work to date at $96,000, which is $5,000 more than the line-by-line total of $91,000.

Four habits keep the per cent honest:

  • Use the lines in your contract. Keep them the same every month, so each claim compares with the last.
  • Measure progress the way the contract says. That might be a schedule of values, stage percentages or measured quantities. If the contract says nothing, agree a method with the client in writing before your first claim.
  • Give every variation its own line and its own status. Claim a variation only when your contract's approval step is done. Whether you can claim an unapproved variation depends on your contract and your state's Act. Ask a lawyer.
  • Write lines that can be checked. A line that names the work is easier to measure than "balance of works". The pricing guide covers scope lines that can be checked.

How to build the claim

Step 1: List every line and its value

Put each contract line and each approved variation on its own row, before GST. The total is the adjusted contract sum.

Step 2: Work out work to date

Multiply each line's value by its per cent complete. Add the rows. No line goes above 100%.

Step 3: Take off retention

Multiply work to date by the retention rate, and compare the result with the cap. Use the lower figure. Subtract the retention already held to find what this claim adds.

Step 4: Subtract previous claims, then add GST

Subtract earlier claims after retention. Keep earlier unpaid amounts on a separate line. If you're registered, add 10% to this month's amount.

A worked example (fictional)

Fictional example. Quandong Lane Plumbing is not a real business. The figures are illustrative and are not a customer result.

Quandong Lane Plumbing is a small plumbing subcontractor, making its second claim to a head contractor. Its contract has three stages and two approved variations. The contract sum is $180,000: rough-in $60,000, fit-off $70,000 and final $50,000. Variation 1 is $8,000 and Variation 2 is $4,000, so approved variations are $12,000 and the adjusted contract sum is $192,000. Every amount excludes GST unless it says otherwise.

The contract also says:

  • Retention is 5% of work to date. The cap is 5% of the adjusted contract sum.
  • Half the retention is released at practical completion and half at the end of the defects liability period.
  • Quandong Lane is registered for GST, at 10%.
  • Claim 1 was for rough-in at 100%: $60,000, less $3,000 retention. The head contractor paid $57,000 in full.
Line Value Per cent complete Work to date Claimed in claim 1 Work in this claim
Rough-in $60,000 100% $60,000 $60,000 $0
Fit-off $70,000 30% $21,000 $0 $21,000
Final $50,000 0% $0 $0 $0
Variation 1 $8,000 100% $8,000 $0 $8,000
Variation 2 $4,000 50% $2,000 $0 $2,000
Total $192,000 $91,000 $60,000 $31,000

Now the claim itself:

Step Amount
Work to date $91,000
Retention to date: 5% × $91,000 −$4,550
Net value to date $86,450
Previous claims after retention −$57,000
This claim, before GST $29,450
GST at 10% $2,945
Claim including GST $32,395

Two checks:

  • The cap. 5% of $192,000 is $9,600. Retention to date of $4,550 is under it, so the cap doesn't apply yet.
  • The other route. This claim's work is $31,000. Retention on it is $4,550 less the $3,000 already held, which is $1,550, and that equals 5% of $31,000. So $31,000 less $1,550 is $29,450 again.

Reading the result

  • The claim is $29,450, not $31,000. $1,550 of this month's work goes into retention. After this claim, the client holds $4,550.
  • A common slip is taking retention twice. Taking the full $4,550 off this month's $31,000 gives $26,450. That is $3,000 short, which is the retention already held from claim 1.
  • Variation status moves the claim. Suppose your contract needs written approval and neither variation has it. Work to date is then $81,000, retention is $4,050 and net value is $76,950. This claim falls to $19,950 before GST, which is $9,500 less.
  • The cap's base matters. If the cap used the contract sum without variations, 5% of $180,000 would be $9,000. That is $600 below $9,600. Whether approved variations count in a cap is a question for your contract and the regulator.
  • Retention comes back later. If every line reached 100%, work to date would be $192,000 and retention would be $9,600, the same as the cap. Under this contract, $4,800 would come back at practical completion and $4,800 at the end of the defects liability period.

A claim is not cash. This one is $32,395 including GST, but it lands on the date your contract and your state allow, and retention lands later still. Our Payday Super cash check for trades lines up those weeks against wages and super. Enter each amount on the date you expect to be paid, as step 3 of the cash runway check does.

Retention: what's held, and when it comes back

Your contract sets the retention rate, any cap and the release dates. Some states then limit what a contract can do.

  • Queensland. QBCC's contractor guide (April 2022) says retention and security generally must not exceed 5% of the contract price before practical completion, and 2.5% after. It also says you are "only able to withhold 10 per cent of cash retentions from each progress payment". The guide doesn't say whether approved variations count in the contract price. QBCC's retentions page says the default is release 12 months after practical completion if the contract has no defects liability period. It also says it is an offence not to release retention without reasonable excuse.
  • New South Wales. The NSW retention money page says head contractors must hold retention money in a trust account on projects valued over $20 million. We read no NSW percentage cap.
  • Victoria. The Victorian page read for this guide doesn't cover retention, and we haven't verified a Victorian retention rule.
  • Claiming it back. QBCC says a contract may set reference dates for claiming retention, for example at the end of a defects liability period. Note those dates when you sign the contract, and set a reminder for each one.

What each state says about the claim

Security of payment law is state law. The points below describe what each page says on 3 November 2026, not what a court would decide. If you're unsure which applies to a claim, ask a lawyer.

New South Wales: Building and Construction Industry Security of Payment Act 1999 (NSW)

  • A claim is written, states the amount due and describes the work, goods or services you are claiming (NSW Government, "Making a payment claim", section 13).
  • On the statement that the claim is made under the Act, the two NSW pages differ. The "Making a payment claim" page lists the words for a subcontractor whose contract is connected with a residential construction contract. The "Changes to Security of Payment laws" page says all payment claims must now state it. Ask a lawyer which applies to you.
  • If the contract sets no claim dates, the reference date is the last day of each month. Only one claim can be made for each reference date.
  • A head contractor serving a claim on a principal must give a supporting statement.

Victoria: Building and Construction Industry Security of Payment Act 2002 (Vic), amended on 15 April 2026

This comes from Adjudicate Today, an authorised nominating authority, not from the regulator. Its page says it applies to claims made on or after 15 April 2026.

  • Identify the work, goods or services, including items and quantities.
  • Indicate the amount due, and GST if it applies.
  • Contain the words "This is a payment claim made under the Building and Construction Industry Security of Payment Act 2002 (Vic)".
  • Be addressed to the legal entity or person you contracted with, not a trading name, with the correct ABN or ACN.
  • Be served under the Act's service rules.
  • A claim can be served from the last day of the named month in which work was first carried out. After that, it can be served from the last day of each named month in which work is carried out. A claim served early is taken to be served on the earliest day.

Queensland: Building Industry Fairness (Security of Payment) Act 2017 (Qld)

QBCC's "Request payment" page was last reviewed on 31 August 2021, so check for changes.

  • A claim is a written request for payment that identifies the work or goods and services, states the amount and requests payment. QBCC says to check that your usual tax invoice meets these three points.
  • You claim on or after a reference date. That is the date in your written contract or, if there is none, the last day of the month the work was done. Only one claim can be given for each reference date.
  • A claim can include work to the reference date and outstanding amounts from earlier claims.
  • A claim submitted before a reference date may be invalid, and may limit your access to adjudication.
  • Head contractors on non-residential contracts must give a supporting statement with a claim to a principal.

What this guide doesn't do

  • It isn't a payment claim. A spreadsheet works out the amount. Whether a claim meets your state's Act, including its wording, the right legal entity, service and timing, is a separate test.
  • It covers three states, on dated pages. We haven't covered Western Australia, South Australia, Tasmania, the ACT or the Northern Territory. One QBCC page was last reviewed in 2021 and its contractor guide is from April 2022. Victoria's Act changed on 15 April 2026. Check the current rules before you rely on any of them.
  • It doesn't settle GST on retention. Ask your registered tax or BAS agent how GST should show on a claim where retention is held back.
  • It doesn't decide disputes. It can't tell you whether a variation is claimable or whether the client will accept your per cent complete. For a specific claim, ask a lawyer, QBCC or your state's authorised nominating authority.
  • It's written for subcontract work. Contracts with homeowners can have their own rules. Check with your state regulator.

A workbook for this, in research

We're researching a workbook for this. It isn't built, and there's no price or date. If you'd like one email when it's ready, or one saying we've decided not to build it, join the waitlist.

Independence

Metricvalley is independent. This guide isn't affiliated with, or endorsed by, any state or territory government, the QBCC, or any nominating authority. Nothing in it is legal, tax or accounting advice.

Sources

Every other figure in this guide comes from the fictional worked example.

Common questions

Do I add GST to a progress claim?

If you're registered for GST, yes. GST is 10% of the price, and you collect it from your customer. You must register if your GST turnover is $75,000 or more. Below that, you don't include GST unless you chose to register. How GST should show on a claim with retention held back is a question for your registered tax or BAS agent.

How much retention comes off a progress claim?

Multiply work to date by the retention rate in your contract, and stop at any cap. Then subtract the retention already held from earlier claims. In the example, 5% of $91,000 is $4,550, less $3,000 already held, so $1,550 comes off this claim. Queensland, for one, sets limits, so check your state's rules.

What if my last claim hasn't been paid yet?

Subtract what you claimed, not what you were paid, so this month's figure covers only new work. Show the unpaid amount on its own line below it. The NSW and Queensland pages read for this guide say a claim can include earlier unpaid amounts. Check your contract and your state's Act before you carry an amount forward.