How to price a project so it still pays after delivery
A quote can look healthy and still deliver less once the hours are in. Build it from loaded cost rates, checkable scope lines, a separate contingency line and direct costs, then compare it with what happened.
The gap between a quote and what it delivers rarely comes from one big mistake. It comes from four small ones: rates that don't carry their full cost, scope lines that are too loose, no room for the unknown, and direct costs added after the price is set.
This guide walks through each part of a quote, then shows a fictional project from quote to final hours, so you can see where quoted margin and delivered contribution part ways.
Start from a loaded cost rate
Every hour you quote needs a cost behind it: a loaded cost rate, which is a person's full annual employment cost divided by the hours they actually spend on client work. How to set an internal hourly cost rate shows the full method, including owners and freelancers.
Fictional example. A designer earns US$72,000. Employer costs add US$14,400, for a total of US$86,400. After 200 hours of holidays and leave, they have 1,880 paid hours. About 70% of those go on client work, which is 1,316 delivery hours. The loaded cost rate is US$86,400 ÷ 1,316, or about US$66 an hour.
Dividing pay alone by 2,080 would give about US$35. Quoting from that figure would undercount this person's cost by almost half.
This cost rate stops before overhead. Rent, software, insurance and the owner's admin time are covered by the margin you add on top, which is the next step.
Set a margin target you can defend
Contribution margin is fee minus delivery cost, divided by fee. To price for a target margin:
Price = delivery cost / (1 - target contribution margin)
Set the target from your own books: with overhead at about 30% of fees and 15% wanted after it, you need about 45%. Markup vs margin shows why a 50% markup is only a 33% margin, and how to set the target from your cost rate and overhead.
Write scope lines that can be checked
A scope line is a promise you can measure later. Each one should name:
- The deliverable, in plain words ("homepage and four inner page designs")
- The role doing it and the hours estimated
- The number of revision rounds included
- What is assumed ("client supplies final copy by week 3")
- What is excluded ("photography, hosting, content migration")
Loose lines such as "website design" can't be checked against actual hours, and they give no clear point at which extra work becomes a change request. Tight lines let you say, calmly, "the third round of design changes is outside the quote, here is the cost".
Keep contingency on its own line
Contingency covers the unknown: a slower approval, a tricky integration, a stakeholder who joins late. Show it as a separate line, not padded into each estimate. That way you can see after the project whether it was used, and how much.
Size it from your own history. Compare past estimates with actual hours for similar work. If you have no history yet, choose a figure, write it down, and check it after the next few projects. Work you have done many times needs less than work you have never done.
List direct costs before you set the price
Direct costs are what you pay out for this project alone: freelancers, stock images and fonts, printing, travel, software licenses bought for the job, and any media spend you pass through.
For each one, decide whether you pass it through at cost or add a markup, and say so in the quote. If a freelancer invoices in another currency, note the rate you used and the date. A cost added after the price is set comes straight out of contribution.
A quote sheet structure that holds up
Whatever tool you use, a quote sheet that you can check later has these parts, in this order:
- Header. Client, project, date, version, currency and any exchange rate used.
- Scope lines. Deliverable, role, hours, cost rate and cost for each line.
- Contingency. Hours and cost, as its own line.
- Direct costs. Each cost, with pass-through or markup noted.
- Total delivery cost. Labor, contingency and direct costs.
- Target margin and price. The price formula, then the rounded price.
- Quoted margin. Recalculated from the rounded price.
- Terms. Payment schedule, revision rounds, assumptions, exclusions and how long the quote is valid.
Keep the sheet after the project is signed. It is the baseline you compare actual hours against.
A worked example: quote vs delivery
Fictional example. A studio quotes a website project. Cost rates are US$80 an hour for the strategist, US$66 for the designer and US$75 for the developer. Contingency is 10% of labor, direct costs are a freelance copywriter (US$1,200) and stock images (US$300), and the target contribution margin is 45%.
Total delivery cost comes to US$13,919. At 45%, the price is US$13,919 ÷ 0.55, or US$25,307, which the studio rounds up to US$25,500. Here is the quote next to what happened:
| Line | Quoted hours | Quoted cost | Actual hours | Actual cost |
|---|---|---|---|---|
| Discovery (strategist) | 12 | US$960 | 12 | US$960 |
| Design, 2 revision rounds (designer) | 60 | US$3,960 | 78 | US$5,148 |
| Build (developer) | 70 | US$5,250 | 80 | US$6,000 |
| Project management (strategist) | 14 | US$1,120 | 18 | US$1,440 |
| Contingency, 10% of labor | 15.6 | US$1,129 | — | — |
| Direct costs | — | US$1,500 | — | US$1,900 |
| Total delivery cost | 171.6 | US$13,919 | 188 | US$15,448 |
| Contribution on US$25,500 | US$11,581 (45.4%) | US$10,052 (39.4%) |
The figures are illustrative and are not a customer result.
Quoted margin and delivered contribution are different numbers
Quoted margin is a plan: what the project leaves if the hours and costs match the estimate. Delivered contribution is what it actually left after the last hour and invoice.
In the example, the gap is six points, or US$1,529. It came from four places:
- Design, +18 hours. The client asked for a third revision round. The quote included two, so this should have been a change request.
- Build, +10 hours. An integration took longer than estimated. This is the kind of overrun contingency is for.
- Project management, +4 hours. Extra calls followed the added design round.
- Copywriting, +US$400. The freelancer billed for a second pass on the new pages.
Actual labor ran 32 hours over the scope lines, about twice the 15.6 hours of contingency. Contingency absorbed the build overrun. The design round, which was outside scope, is what pushed the project below its target.
Two changes would have kept most of the margin. First, billing the third revision round as a change request. Second, recording actual hours against each scope line as the project ran, so the design overrun showed up in week 3 instead of at the end.
Close the loop after every project
Put the final hours next to the quote sheet and note three things: which lines ran over, whether contingency was enough, and whether any work should have been a change request. After a few projects, those notes become your contingency percentage and your standard revision limits.
For the month-by-month view across all clients, the Client Profitability Tracker shows delivered contribution before overhead by client, project and month. The method behind it is in client profitability: contribution before overhead. Retainers need a different check during the month; see how to tell when a retainer is underwater.
What this method doesn't do
- It doesn't make your estimates right. Contingency covers overruns only up to its size. Work beyond the scope lines still needs a change request, and you have to raise it.
- It doesn't check your margin target. If your overhead share is wrong, a quote can hit its target and still leave too little after overhead.
- It doesn't show cash timing. The payment schedule sits in the terms. The method doesn't compare when the client pays with when you pay staff and freelancers.
- It doesn't protect a quote from currency moves. Noting the rate for a freelancer who bills in another currency records your assumption. If the rate moves before you pay, the cost changes.
- The Terms part of the quote sheet is a checklist, not contract wording. For the contract itself, ask a lawyer.
A calculator for this
The Project Quote Calculator builds a quote from loaded rates, scope lines, contingency and direct costs, and shows the quoted margin before you send it. Its page shows every sheet and where it has been tested. The quote sheet above also works in any spreadsheet.
Sources and method
Every figure in this guide comes from its fictional examples. The price formula is standard contribution-margin arithmetic: contribution is the fee minus delivery cost, and the margin is contribution divided by the fee.
- OpenStax, 3.1 Explain Contribution Margin and Calculate Contribution Margin per Unit, Contribution Margin Ratio, and Total Contribution Margin (textbook: Principles of Accounting, Volume 2: Managerial Accounting), read Oct 2, 2026.
Update history
- : Updated the spreadsheet section: the Project Quote Calculator is now on sale.
- : Added a section on what this method doesn't do.
- : Shortened the cost-rate and margin-target sections, which now link to the guides that cover them in full. Replaced the markup and margin question with one on showing contingency to a client. Added a Sources and method section.
Common questions
What is a loaded hourly rate?
A loaded hourly rate is what one delivery hour really costs you. Take a person's full annual employment cost, including pay, employer taxes and benefits, and divide it by the hours they actually spend on client work in a year. It is usually well above their pay divided by 2,080 hours.
Should a quote show the contingency line to the client?
Either can work. What matters is that contingency stays a separate line on your own quote sheet. On a fixed fee, you can fold it into the price the client sees and still track it internally. On hourly or capped work, showing it as an allowance the client approves before you use it makes the extra hours easier to agree. Write down which approach the quote uses.
How much contingency should a project quote include?
Base it on your own history. Compare past estimates with actual hours for similar work and use the typical overrun as your starting percentage. With no history, pick a figure, write it down as its own line, and check it against actuals after the next few projects.
How we research, check and update these guides. Found an error? Email [email protected] and we’ll correct it and note the change here.