December capacity: can you deliver with people on leave?
You can deliver in December when each person's client hours, after holidays and leave, cover the retainer and project hours booked for them. Count working days first, then check person by person in November.
Your retainers don't pause for the holidays. Your people do. One person is off for a week, two are off for two, and the retainer work is still due in the last week of December.
This guide shows how to check that in November. Count December's working days. Turn them into client hours for each person. Set those against the retainer and project hours booked for that person. A fictional studio works through every step, then closes a gap in four ways.
Count working days before hours
Start with the calendar, not the plan. December 2026 starts on a Tuesday and has 23 weekdays.
Take out the public holidays your team takes. The U.S. Office of Personnel Management's list of federal holidays has one date in December 2026: Friday, Dec 25. That leaves 22 working days.
Working days = weekdays - public holidays - that person's days off
Private businesses set their own holidays. The Department of Labor says the Fair Labor Standards Act doesn't require pay for holidays or vacations. It adds that these are generally a matter of agreement with your staff. So use the days your team gets, not the federal list. If your studio also closes on Thursday, Dec 24 or Thursday, Dec 31, those are days off for everyone.
Count by week too. Leave rarely falls evenly, and the weeks show where the hours are.
| Week | Dates | Weekdays | Holidays | Working days |
|---|---|---|---|---|
| 1 | Dec 1–4 | 4 | 0 | 4 |
| 2 | Dec 7–11 | 5 | 0 | 5 |
| 3 | Dec 14–18 | 5 | 0 | 5 |
| 4 | Dec 21–25 | 5 | 1 | 4 |
| 5 | Dec 28–31 | 4 | 0 | 4 |
| December | 23 | 1 | 22 |
Outside the US, use the public holiday list for where each person works. GOV.UK lists Friday, Dec 25 and a substitute Boxing Day on Monday, Dec 28 for England and Wales, which leaves 21 working days. In Australia, public holidays differ by state and territory, and the Fair Work Ombudsman lists them for each.
Client hours for each person
A working day isn't a client day. Some of it goes to email, internal meetings and admin. Use the client hours a day your people actually log, by role if you can. The utilization target guide shows how to set them.
Client hours = working days × client hours a day
Booked hours = retainer hours + project hours
Balance = client hours - booked hours
Book each retainer at the hours it has used lately, not the hours in its contract. A retainer that has run over for three months will probably run over in December. How to tell when a retainer is underwater shows how to read that.
Work out the balance for each person. Read the team total last.
A worked example (fictional)
Fictional example. Hollin Quay Studio is not a real business. The figures are illustrative and are not a customer result.
Hollin Quay is a four-person design and web studio. In early November it plans December 2026. Everyone gets 6 client hours a day, which is 6 of 8 hours, or 75%.
All the leave falls from Dec 21. The designer and the writer are off Dec 21 to 24 and Dec 28 to 31, which is 8 days each. The developer is off Dec 24 and Dec 28 to 31, which is 5 days. The account lead is in all month.
- Working days. The month has 22 working days after Christmas Day. Take off each person's days off.
- Client hours. Multiply each person's working days by 6.
- Booked hours. Add each person's retainer hours and project hours from the plan.
- Balance. Client hours less booked hours.
| Person | Days off | Working days | Client hours | Retainers | Projects | Booked | Balance |
|---|---|---|---|---|---|---|---|
| Account lead | 0 | 22 | 132 | 114 | 6 | 120 | +12 |
| Developer | 5 | 17 | 102 | 92 | 24 | 116 | −14 |
| Designer | 8 | 14 | 84 | 80 | 30 | 110 | −26 |
| Writer | 8 | 14 | 84 | 74 | 30 | 104 | −20 |
| Studio | 21 | 67 | 402 | 360 | 90 | 450 | −48 |
The steps for each person:
- Account lead: 22 − 0 = 22 working days. 22 × 6 = 132 client hours. 114 + 6 = 120 booked. 132 − 120 = +12.
- Developer: 22 − 5 = 17. 17 × 6 = 102. 92 + 24 = 116. 102 − 116 = −14.
- Designer: 22 − 8 = 14. 14 × 6 = 84. 80 + 30 = 110. 84 − 110 = −26.
- Writer: 22 − 8 = 14. 14 × 6 = 84. 74 + 30 = 104. 84 − 104 = −20.
The studio has 402 client hours (132 + 102 + 84 + 84) and 450 booked hours (360 of retainers and 90 of projects). It is 48 hours short. It is booked at 450 ÷ 402 = 111.9% of its client hours. The designer is booked at 110 ÷ 84 = 131.0%.
The hours also bunch up early. The first three weeks, Dec 1 to 18, have 14 working days with all four people in. That is 4 × 14 × 6 = 336 client hours, or 83.6% of December's 402. The last two weeks have the other 66: the account lead's 48 and the developer's 18. The designer and the writer have none.
Reading the result
The team total says 48 hours short. The first fix that comes to mind is to move 48 hours of project work to January. Say the clients agree. Hollin Quay takes 14 hours off the developer's projects, 14 off the designer's and 20 off the writer's.
| Person | Client hours | Booked after the move | Balance |
|---|---|---|---|
| Account lead | 132 | 120 | +12 |
| Developer | 102 | 102 | 0 |
| Designer | 84 | 96 | −12 |
| Writer | 84 | 84 | 0 |
| Studio | 402 | 402 | 0 |
The team total now reads 0. The designer is still 12 hours over: 96 booked against 84. The account lead has 12 spare hours, and they can't do design. On paper, one person's spare hours cancel another's shortfall. In the week, they don't. The same is true in a normal month, but leave makes the gaps larger, because it takes more hours from some roles than from others.
Three mistakes to avoid:
- Planning from contract hours. A retainer booked at its contract hours looks lighter than it is when it has been running over.
- Reading the team total only. It can read zero while one role is 12 hours over.
- Treating zero as safe. A balance of 0 means booked to the last client hour. A sick day costs 6 hours, and nobody has any spare. If you want a buffer, subtract it from client hours before you start.
Four fixes
Try them in this order. The first two need no new spend.
- Move. Push project hours that nobody needs before the new year into January. Check January first. It has 21 weekdays. The 2027 federal list has two January holidays: New Year's Day on Friday, Jan 1 and Martin Luther King Jr.'s Birthday on Monday, Jan 18. If your studio takes both, that leaves 19 working days. Run the same sum for January before you promise anything. Hollin Quay moves 48 hours, as above.
- Front-load. Match the work to the weeks people are in. The designer and the writer have 24, 30 and 30 client hours in weeks 1 to 3, and none after. Ask what each client expects from them after Dec 18. Finish it by Friday, Dec 18, or move it to someone who is in.
- Cover. Bring in a freelancer for what is left. Hollin Quay books a freelance designer for the designer's last 12 hours, which leaves the designer at 84 of 84. Put the freelancer's invoice against the client it serves. How to set an internal hourly cost rate shows how to record freelancers.
- Tell the clients. Do this with whichever fix you choose, and do it in November.
After the three fixes, the developer, the designer and the writer are each booked to their last client hour. The account lead's 12 spare hours are the only buffer in the plan.
A December plan to send clients in November
Put it on one page. Say four things:
- When people are away.
- What you will finish by when.
- What moves to January.
- The date you need the client's input by.
Send it in November, while January still has room and clients can plan around the dates. Then you can still change the plan before the leave starts.
Here is a version for Hollin Quay's retainer clients. Fill in the brackets for each one.
Subject: Your December plan
We're working as normal through Friday, Dec 18. From Monday, Dec 21 the studio runs with fewer people, and we're closed on Friday, Dec 25. From Dec 28 to 31, [name] covers anything that breaks. We're back at full strength on Monday, Jan 4.
By Dec 18 we'll finish: [list]. In January we'll start: [list]. If you need something in December, please send it by Friday, Dec 11, so it lands while the right people are in.
If any of these dates doesn't work for you, reply and we'll change the plan this week.
Clients take leave too. If feedback arrives late, the work lands after the hours are gone, so ask for approvals early.
What this method doesn't do
- It counts booked leave, not sickness. A sick day in the last week costs 6 hours from someone whose week is already full. Add a buffer if you want one.
- It rests on your estimates. Client hours a day and booked hours are guesses until you log them. Last December's logs, if you have them, are a better start than a round number.
- It doesn't schedule days or tasks. The weekly split shows when hours exist. It doesn't say who does what on which day.
- It doesn't know your clients' leave. A client who is away can't approve work, and the hours move.
- It doesn't say whether a retainer's fee covers its hours. It checks capacity, not price. A retainer can fit December and still be underpriced.
- It doesn't settle what holiday or leave pay your staff are owed. That depends on where they work and on your agreements. Ask an employment lawyer or adviser.
A planner for this
The Retainer Burn & Capacity Planner works out each person's client-work hours for next month, after their time off and the public holidays you list. It sets them against the retainer and project hours already planned for that person. It takes hours you have already tracked and doesn't record time. It is an Excel 365 workbook, and you type or paste the hours in. It plans by month, so it shows each person's December balance and not which week the hours fall in. It spreads each person's weekly hours evenly over Monday to Friday and applies public holidays to everyone, so part-time days and regional holidays are approximate. Its page lists where it has been tested.
The method above works in any spreadsheet. One row per person is enough: working days, client hours, booked hours and balance.
Independence
Metricvalley is independent. This guide isn't affiliated with, or endorsed by, the U.S. Office of Personnel Management, the U.S. Department of Labor, the Fair Work Ombudsman or GOV.UK. Nothing in this guide is financial, tax, employment or legal advice.
Sources and method
Every figure in the worked example is fictional (Hollin Quay Studio). Weekdays are counted from the calendar. The holiday dates come from the sources below. The client hours a day, the leave, the bookings and the 48-hour move are the example's own assumptions.
- U.S. Office of Personnel Management, Federal Holidays (no page date shown), read Nov 3, 2026.
- U.S. Department of Labor, Holiday Pay (no page date shown), read Nov 3, 2026.
- Fair Work Ombudsman, Public holidays (page updated Oct 28, 2026), read Nov 3, 2026.
- GOV.UK, UK bank holidays (page updated Nov 24, 2025), read Nov 3, 2026.
Common questions
How many working days does December 2026 have?
December 2026 has 23 weekdays. Friday, Dec 25 is a federal holiday, which leaves 22 working days if that is the only day your team takes. Take out any other days your studio closes, such as Dec 24 or Dec 31. Then take out each person's days off before you multiply by their client hours a day.
Should you plan December capacity by person or by team?
By person. A team total can read as balanced while one role is full, because a developer's spare hours can't do design work. Work out each person's client hours after leave, set them against the work booked for that person, and read the team total last.
When should you tell clients about December?
Send the plan in November, while January still has room and clients can plan around the dates. Say when the studio is closed, what will be finished by when, and what moves to January. Ask clients to reply if a date doesn't work, so you can change the plan before the leave starts.